2025 Public Works and County Paving Projects
Project Summary
The scope of this project consists of two schedules:
Public Works Projects – The City of Normandy Park desires to complete a variety of capital improvement projects in 2025 to include beam guardrail improvements, basketball court, parking lot improvements, Public Works Shop site paving improvements, sidewalk replacements and intersection/ storm improvements.
King County Pavement Projects – The City of Normandy Park utilizes King County’s Road Services Division to contract paving projects. The County’s contractor is slated to complete the work in late summer.
Thank you in advance for your patience and cooperation. If you have any questions, please feel free to contact Public Works Director Ken Courter (206) 248-8269 or Stormwater Coordinator Jessie Medrow (206) 248-8256.
Project Update
July 31, 2025
Upcoming Road Work – August 5–15, 2025
Paving work will begin on Tuesday, August 5. The City is working closely with the County and their contractor to reduce impacts as much as possible. However, please note that we do not control the contractor’s exact schedule, including the specific times and durations of work.
Planned Work Schedule:
-
4th Ave SW (South of SW 174th St)
-
Paving Dates: Tuesday, August 5 & Wednesday, August 6
-
-
SW 174th St (West of 13th Ave SW)
-
Grind & Prep: Thursday, August 7
-
Paving: Friday, August 8
-
-
Marine View Dr (Edgecliff Dr to SW 197th St)
-
Work Dates: Monday, August 11 – Friday, August 15
-
We appreciate your patience during this work and will provide updates if the schedule changes.
Phase 1 – Public Works Projects
Project Timeline
-
-
- Tuesday, May 6, 2025 – City Bid Opening
- Thursday, July 10, 2025 – City’s contractor to begin projects
-
Phase 2 – King County Paving
Project Timeline
-
- Tuesday, May 6, 2025 – County Bid Opening
- Tuesday, August 5, 2025 – County’s Contractor to begin paving:
-
- 4th Ave SW (South of SW 174th St) – Tuesday August 5th and Wednesday August 6th
- SW 174th St (West of the 13th Ave SW) – Thursday, August 7th – Grind and Pavement Prep and Friday, August 8th – Paving
- Marine View Dr (between Edgecliff Dr and SW 197th) Monday, August 11th – Friday, August 15th
Project Location:
See Map
Phase 1 – Public Works Projects
Expected Start Date:
07/10/2025
Expected Completion: Date:
09/05/2025
Phase 2 – King County Paving
Expected Start Date:
08/06/2025
Expected Completion Date:
08/26/2025
Contacts
Ken Courter
Public Works Director
(206) 248-8269
email
Jessie Medrow
Stormwater Coordinator
(206) 248-8256
email