Project Summary

Highline Water District is permitted to replace a watermain at SW 191st St (west of 4th Ave SW).  This project is taking place prior to the King County Overlay.

HWD has been instructed to notify any property owners of restricted road or driveway access.

For questions or concerns regarding this project, contact Highline Water District directly at 206-824-0375

 

Project Timeline

      • Monday, April 29, 2024
        Highline has notified the city that work is slated to begin late April and last through May 2024.

Project Location:
SW 191st St at 4th Ave SW

Phase 1

Expected Start Date:
04/29/24

Estimated Completion: Date:
05/31/24