First Avenue South Overlay Project

Jessie Medrow
January 31, 2020
Normandy Park 168th Westside Ramp

1st Ave S Overlay Project from SW 174th St to Burien Normandy Park 1st Ave Curb Ramp Retrofit and WW 168th St Drainage Improvements.

The first phase of this project consists of the construction of curb ramps at three intersections along 1st Ave South, one curb ramp at the intersection of 6th Avenue SW and SW 186th Street; and storm drainage improvements including new pipe, catch basin, and ditch regrading at various locations on 12th Avenue SW and SW 168th Street. The 1st Avenue South curb ramp retrofit project is to be constructed in advance of a King County overlay project.

Project Update

September 29, 2020

King County completed the asphalt overlay at the end of August.  The only items left to complete consist of minor restoration and lane striping.

Thursday, July 16, 2020

King County’s contractor, ICON, will begin pavement restoration work on Monday, July 20, 2020.

This road resurfacing project includes the following areas:

  • 6th Ave SW from SW 186th St to SW 189th St (to include SW 187th St and SW 189th St)
  • 1st Pl SW and 2nd Pl SW south of SW 190th St
  • SW 168th St from 12th Ave SW to 19th Ave SW
  • 12th Ave SW from SW 168th St to SW 170th St
  • 19th Ave SW from SW 168th St to SW 170th St

Learn more about Normandy Park’s Capital Projects by visiting our Current Projects page. Thank you in advance for your patience and cooperation. Please contact Public Works Director Ken Courter (206) 248-8269 with any questions.

June 1, 2020 – Normandy Park 1st Ave Curb Ramp Retrofit and Stormwater Drainage Upgrade

Work is scheduled to start June 1st and end mid-July followed by King County’s Overlay Project.

Project Description

The scope of this project consists of Schedules A and B. Schedule A involves the removal and replacement of curb and gutter, curb ramps, and sidewalks along 1st Ave S at SW 164th Pl, S 168th St, and S 170th St starting June 1st. Schedule B is the removal and replacement of curb and gutter, curb ramps, sidewalk, and storm drainage upgrades along SW 186th St at 6th Ave SW and SW 168th St at 12th Ave SW, 15th Ave SW, and 19th Ave SW.

Expect traffic control flaggers and lane closures along northbound and southbound 1st Ave S and single lane access at all other project locations. At times, driveway access may be limited and everything will be done to assist property owners with access.

Thank you in advance for your patience and cooperation. If you have any questions, please feel free to contact Public Works Director Ken Courter (206) 248-8269 or Environmental Specialist Jessie Medrow (206) 248-8256.

    Contacts

    Ken Courter
    Public Works Director
    (206) 248-8269
    email

    Jessie Medrow
    Stormwater Coordinator