Walker and Sequoia Creek Culverts Replacement Project
Project Summary
The Walker and Sequoia Creeks realignment projects consists of three phases: design, property acquisition, and construction. In 2020, consultant Gray & Osborne, Inc. prepared a technical memo after evaluating whether two existing culverts had the capacity to convey peak stormwater flow. The culverts have been identified as partial fish barriers that are undersized to convey flows from Walker Creek and its tributary, Sequoia Creek. The existing culverts will be removed and replaced with a bridge at 12th Avenue SW (over lower Walker and Sequoia Creeks) and a box culvert at SW 174th Street (to convey upper Sequoia Creek) that will be designed to provide fish passage.
Washington Department of Fish and Wildlife (WDFW) has identified the following species in Walker and Sequoia Creeks that are listed as Threatened under the Endangered Species Act (ESA): Puget Sound chinook salmon and steelhead. Additionally, the Creeks are habitat for the following species that have been identified as Priority Species by WDFW: resident coastal cutthroat, fall chum salmon, and coho salmon.
12th Avenue SW – The Project will remove three under-sized culverts that convey Walker and Sequoia creeks across 12th Avenue SW, and replace them with a bridge. The existing culverts impede fish passage and cause flooding of the roadway and adjacent properties during storm events every several years. The proposed bridge will improve access to 415 meters of Walker Creek and 235 meters of Sequoia Creek for anadromous salmonids. Property acquisition has been funded through a combination of a grant through the King County Conservation Futures and local funding. That property acquisition will be complete in 2023. Demolition of existing structures on the site has been funded by a Cooperative Watershed grant from the King County Flood Control District. Construction of the proposed bridge is planned for 2024.
SW 174th Street – The Project will remove an under-sized culvert that conveys Sequoia Creek across 174th Avenue SW. The existing culvert is subject to frequent plugging with debris, which further impedes fish passage and access to 300 meters of anadromous salmonid habitat. Construction of the proposed box culvert is planned for 2025.
If you have any questions, please feel free to contact Public Works Director Ken Courter (206) 248-8269 or Stormwater Coordinator Jessie Medrow (206) 248-8256.
Phase 1 – Design (Complete)
Project Update
-
- September 2024 – 90% Design has been completed
- August 2022 –The City of Normandy Park has completed 60% design for the replacement of undersized culverts at two locations:
- 12th Avenue SW – A bridge that will replace two existing 18-inch culverts that convey Sequoia Creek and one 24-inch culvert that conveys Walker Creek in the vicinity of 12th Avenue SW and SW Eastbrook Road. Sequoia Creek will be realigned to allow it to discharge directly to Walker Creek.
- SW 174th Street – A new box culvert will replace an existing 24-inch culvert that conveys Sequoia Creek across SW 174th
Project Timeline & Funding Sources
-
- 2020 King County Flood Control District: Flood Reduction Grant (60% Design) – $300,000
- 2021 King County Flood Control District: Flood Reduction Grant (90% Design) – $200,000
- 2022 King County Flood Control District: Flood Reduction Grant (100% Design to be completed in 2023) – $150,000
Phase 2 – Property Acquisition and Demolition (Complete)
Project Update
-
- September 2024 – Demolition and site stabilization scheduled. All structures will be removed.
- December 2022 – Purchase and Sale Agreement Signed
Council approved the PSA for the property acquisition of 17622 12th Ave SW at the December council meeting.
Project Timeline & Funding Sources
-
- 2021 King County Conservation Futures Grant received – $600,000
- 2019 – 2022 King County Parks Levy Funds – $521,543
- REET Funds – $212,757
- 2022 Cooperative Watershed Management Grant awarded to Normandy Park for demolition and site stabilization – $150,000
Phase 3 – Construction (Pending Grant Funding)
Project Update
-
- September 2024 – The City submitted an application to the Federal Highway Administation for Grant Funding
- February 2023 – The City submitted an application to the Federal Highway Administation for Grant Funding (Not selected for grant funding) Removal, Replacement, and Restoration Grant Program (Culvert AOP Program)
Project Timeline & Funding Sources
-
- 2024 – Estimated start date of demolition and site prep
- 2026 – Estimated start date of construction at the 12th Ave SW location, pending grant funding
- 2027 – Estimated start date of construction at the SW 174th Street location, pending grant funding
- 2027 – Once the culverts are replaced, property is to be converted to open space park with trails and interpretive signs for the public to enjoy.
Project Location:
Walker Creek at 12th Ave SW and Sequoia Creek at SW 174th St
Expected Project Timeline:
2026-2027 Construction Phase
2024-2025 Demolition and Site Prep
2023-2024 Property Acquisition
2020-2023 Design and Permitting
Contacts
Ken Courter
Public Works Director
(206) 248-8269
email
Jessie Medrow
Stormwater Coordinator
(206) 248-8256
email